Question: Exercise #2 - Build the Flow and Confirm Critical Path Task ID Task Description Project start A B Buy materials for A C Buy materials

Exercise #2 - Build the Flow and Confirm Critical

Exercise #2 - Build the Flow and Confirm Critical Path Task ID Task Description Project start A B Buy materials for A C Buy materials for B D Build A E Build B F Polish and finish B G Join A and B H Project finish Task Duration Task Predecessors (hours) A A B, C B, C E D, F G 0 10 20 30 20 40 20 0 Activate W Go to Setting