Question: Exercise #2- Build the Flow and Confirm Critical Path Task ID A B D E F G H Task Description Project start Buy materials for

Exercise #2- Build the Flow and Confirm Critical

Exercise #2- Build the Flow and Confirm Critical Path Task ID A B D E F G H Task Description Project start Buy materials for A Buy materials for B Build A Build B Polish and finish B Join A and B Project finish Task Predecessors A A B, C B, C E D, F G Task Duration (hours) 0 10 20 30 20 40 20 0