Question: Exercise #2 - Build the Flow and Confirm Critical Path Task Duration Task ID Task Description Task Predecessors ( hours) I Project start O Buy

Exercise #2 - Build the Flow and Confirm Critical Path Task Duration Task ID Task Description Task Predecessors ( hours) I Project start O Buy materials for A Buy materials for B Build A O 2 8 3 8 9 8 0 Build B O OOWLOI Polish and finish B W Join A and B Project finish