Question: Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) A 4 - B 4 - C 5 - D 4 -

Following information is available about a project.

Activity

Activity Time (weeks)

Immediate Predecessor(s)

A

4

-

B

4

-

C

5

-

D

4

-

E

6

A

F

2

B,C,D

G

4

E.F

H

6

F

I

1

G,H

Compute slack for noncritical activities for the project and enter them in the table below.

NOTE: Some rows in table below may be blank.

Activity

Slack

A

B

C

D

E

F

G

H

I