Question: 2. You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network, given the following information. Complete
2. You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network, given the following information. Complete the forward and backward pass, compute activity slack, and ldentify the critical path. How longy will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical actuvities