Question: veloping a Project Plan 12. You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network given
veloping a Project Plan 12. You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calcu- late the free slack and total slack for all noncritical activities. ID A B Time (days) 2 1 2 Description Systems design Subsystem A design Subsystem design Subsystem design Program A Program 8 Pruyan Subsystem A test Subsystem B test Subsystem C test Integration Integration test Predecessor None A A B D E F G HI K WONNEN 1