Question: You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network, given the following information. Complete the
You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network, given the following information. Complete the forward and backward pass, compute activity slack, and identify the critical path.
How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities.
tableIDDescription,Predecessor,Time daysASystems design,None,BSubsystem A design,ACSubsystem B design,ADSubsystem C design,AEProgram ABFProgram BCGProgram CDHSubsystem A test,EI Subsystem B test,FJSubsystem C test,GK Integration,H I, JL Integration test,K
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock