Question: 27. There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed
27. There are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Activties G, H, J, K, S and L can be crashed by 113 days. The maximum possible reduction in the project duration will be:
a.
0 days
b.
Insufficient information
c.
226 days
d.
678 days
e.
113 days