Question: 2.Amir was originally assigned to a Fixed Duration Task that was estimated to take 3d of Duration to complete. This equates to 24 hours of
2.Amir was originally assigned to a Fixed Duration Task that was estimated to take 3d of Duration to complete. This equates to 24 hours of Work at 100%. Amir has reported that it will take him 32 hours to complete the task. What happens to Duration, Work, and Units when the hours of Work is changed to 32 hours and you press OK. What does the red man indicator mean?
Duration =3d Work =24 h, Units = 100% Amir gets the job done.
Duration =4d, Work =32hours, Units =100% Amir is not overallocated
Duration =2d, Work =32hours, Units =200% Amir is crazy.
Duration =3d, Work =32h, Units =133% Amir is overallocated