Question: 3 . 7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows:ImmediatePredecessorsActivityABCGTime ( in hours ) 6
Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows:ImmediatePredecessorsActivityABCGTime in hoursAB C B CDB Fgsa Draw the project network using AON.b Identify the critical path.c What is the expected project length?d Draw a Gantt chart for the project.