Question: 3 . 7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows:ImmediatePredecessorsActivityABCGTime ( in hours ) 6

3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows:ImmediatePredecessorsActivityABCGTime (in hours)6.07.25.06.04.57.74.0AB, C B, CDB, Fgsa) Draw the project network using AON.b) Identify the critical path.c) What is the expected project length?d) Draw a Gantt chart for the project.