Question: Assignment 1 Problem Set ** 3.7 Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows: Activity Time
Assignment 1 Problem Set
** 3.7 Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows:
|
Activity | Time (in hours) | Immediate Predecessor(s) |
| A | 6 | ---- |
| B | 4 | ---- |
| C | 2 | A |
| D | 7 | B,C |
| E | 4 | B,C |
| F | 10 | D |
| G | 2 | E,F |
- Draw the project network using AON.
- Identify the critical path
- What is the expected project length?
- Draw a Gnatt chart for the project