Question: 3. A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table

3. A project network is shown below. Use a

3. A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Precedence Activities Critical Path? ES EF LS LF Slack Activity Time (weeks) 5 4 Activity A B D E F 8 4 12 10 AB DE E EF 3 G H I 2 5 a. Draw the project network. b. Complete a row for each activity under the column headings below. c. Determine the Critical path