Question: A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.
A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks.

| Activity | Precedence Activities | Activity Time (weeks) | ES | LS | EF | LF | Slack | Critical Path? |
| A |
|
|
|
|
|
|
|
|
| B |
|
|
|
|
|
|
|
|
| C |
|
|
|
|
|
|
|
|
| D |
|
|
|
|
|
|
|
|
| E |
|
|
|
|
|
|
|
|
| F |
|
|
|
|
|
|
|
|
| G |
|
|
|
|
|
|
|
|
| H |
|
|
|
|
|
|
|
|
| I |
|
|
|
|
|
|
|
|