Question: A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.

A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks.

A project network is shown below. Use a forward

Activity

Precedence Activities

Activity Time (weeks)

ES

LS

EF

LF

Slack

Critical Path?

A

B

C

D

E

F

G

H

I

A 5 3 D 4 1 5 Stait B 4 F 10 Finish E 12 H 2 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!