Question: 3 - Consider the project as outline in the tables below: c ) Assuming that the indirect cost is $ 8 0 0 0 ,
Consider the project as outline in the tables below:
c Assuming that the indirect cost is $ What is the total project cost after crashing?
NOTE: Total project cost after crashing Project duration after crashing indirect cost sigmasum of each activity time after crashing its normal costweek total crashing cost.
tableActivityPredecessor,tableNormal TimewkstableCrash TimewkstableNormalCost$wkCost to Crash $wkABACADBEBFCGD EH
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
