Question: Project management (3) Consider the following project: Activity Immediate Predecessors A Durations (weeks) 3 A B 3 2 A D B 3 E 7 3

Project management (3) Consider the followingProject management (3) Consider the following

Project management (3) Consider the following project: Activity Immediate Predecessors A Durations (weeks) 3 A B 3 2 A D B 3 E 7 3 F G B,C D, E 6 2 H Which one of the following would expedite the project? Multiple Choice O Expediting D by 2 weeks Expediting B by 1 week Expediting E by 1 week O Expediting H by 1 week