Question: 10.00 points Project management (3) Consider the following project: Activity Immediate Predecessors A Durations (weeks) 6 3 C 2 B 3 E F 8 3

10.00 points Project management (3) Consider the
10.00 points Project management (3) Consider the following project: Activity Immediate Predecessors A Durations (weeks) 6 3 C 2 B 3 E F 8 3 B.C DE G 7 H C 2 Which one of the following would expedite the project? Expediting C by 1 week Expediting by 1 week Expediting B by 2 weeks Expediting F by 2 weeks