Question: please use excel for a-d 3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Predecessors
please use excel for a-d
3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Predecessors Activity A B C D E F Time (in hours) 6.0 7.2 5.0 6.0 4.5 7.7 4.0 A B, C B, C D B.F a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length? d) Draw a Gantt chart for the project P a