Question: 4. A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A ! B

4. A project for improving a billing process has

4. A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A ! B 11 ! 7 A D 13 B.C E 10 B F 6 D 5 G E 8 F G a. Draw the network diagram b. Calculate the slack for each activity. Which activities are on the critical path