Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 5 B 9
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 5 | |
| B | 9 | |
| C | 7 | A |
| D | 11 | B, C |
| E | 10 | B |
| F | 4 | D |
| G | 6 | E |
| H | 9 |
|

b. Calculate the slack for each activity. Which activities are on the critical path?
| Activity | Activity Time (weeks) | On critical path? | Slack (weeks) |
| A | 5 | Yes No | enter your response here |
| B | 9 | No Yes | enter your response here |
| C | 7 | Yes No | enter your response here |
| D | 11 | No Yes | enter your response here |
| E | 10 | Yes No | enter your response here |
| F | 4 | Yes No | enter your response here |
| G | 6 | Yes No | enter your response here |
| H | 9 | Yes No | enter your response here |
PLEASE HELP ME COMPUTE THE SLACK DAYS????
Question 3, Problem 3 Part 2 of 2 HW Score: 39.3%, 8.25 of 21 points Points: 0.35 of 6 Save 10 6 D. Q A 5 S PCB 11 B 10 more help. Clear al Think Manage Scription Seleboble Seite Help G 10:01 PM =Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts