Question: 4) Construct a network using the information in the table and identify the critical path. Activity Time Predecessor A 14 16 B C D E

4) Construct a network using the information in the table and identify the critical path. Activity Time Predecessor A 14 16 B C D E 9 11 16 A B B, C D E, F G F 4 G 8 H 7