Question: Construct a network using the information in the table. Ensure to fill out the table below . What is the critical path for this project?
Construct a network using the information in the table. Ensure to fill out the table below . What is the critical path for this project?

Activity Time Predecessor A 4 B 6 A 9 A D 11 B E 16 B.C F 4 D G 8 E,F H 7 G Task Early Start Early Finish Late Start Late Finish A B D E F G H
Step by Step Solution