Question: 4. Earned value analysis data has been collected for the first 12 weeks of a 24-week project. This is tabulated below. PLANNED ACTUAL Activity BACE


4. Earned value analysis data has been collected for the first 12 weeks of a 24-week project. This is tabulated below. PLANNED ACTUAL Activity BACE PPC% PC% ACWP A 192,000 65 35 125,000 B 37,500 60 75 30,000 C 425,000 20 10 45,000 D 120,000 45 0 25,000 E 525,000 90 75 400,000 65,000 85 70 60,000 G 350,000 25 5 125,000 H 42,000 35 40 35,500 C 35,000 10 5 4000 K 210,000 70 55 130,000 Project 2,001,500 979,500 BAC Budget at completion PPC% Planned % complete PC% Actual % complete ACWP Actual Cost of Work Performed BCWS Budgeted Cost of Work Scheduled BCWP Budgeted Cost of Work Performed EAC Estimate at Completion SV Schedule Variance CV Cost Variance
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
