Question: 4 Problem 5-8 (Algo) Schedule the following activities using CPM: 14.28 points - Print ACTIVITY IMMEDIATE PREDECESSOR A B A C A D B E

4 Problem 5-8 (Algo) Schedule the following

4 Problem 5-8 (Algo) Schedule the following activities using CPM: 14.28 points - Print ACTIVITY IMMEDIATE PREDECESSOR A B A C A D B E CD F D G F H E. G TIME (WEEKS) 3 5 4 2 3 1 1 4 b. What is the critical path? A-C-E-F-G-H A-B-D-F-G-H A-C-E-H A-B-D-E-H c. How many weeks will it take to complete the project? Number of weeks Mc Graw