Question: Problem 5-8 (Algo) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B A 3 C A 6 D B 7
Problem 5-8 (Algo)
Schedule the following activities using CPM:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 4 | |
| B | A | 3 |
| C | A | 6 |
| D | B | 7 |
| E | C D | 3 |
| F | D | 5 |
| G | F | 4 |
| H | E G | 2 |
b.What is the critical path?
multiple choice 1
- A-C-E-G-H
- A-C-E-F-G-H
- A-B-D-F-G-H
- A-B-D-E-H
c.How many weeks will it take to complete the project?
d.Which activities have slack, and how much?
multiple choice 2
- E3 weeksH2 weeks.
- C10 weeksE6 weeks.
- B2 weeksD1 week.
Step by Step Solution
There are 3 Steps involved in it