Question: Problem 5-8 (Algo) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B A 3 C A 6 D B 7

Problem 5-8 (Algo)

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 4
B A 3
C A 6
D B 7
E

C

D

3
F D 5
G F 4
H

E

G

2

b.What is the critical path?

multiple choice 1

  • A-C-E-G-H
  • A-C-E-F-G-H
  • A-B-D-F-G-H
  • A-B-D-E-H

c.How many weeks will it take to complete the project?

d.Which activities have slack, and how much?

multiple choice 2

  • E3 weeksH2 weeks.
  • C10 weeksE6 weeks.
  • B2 weeksD1 week.