Question: 5. Gantt charts cannot depict float. Select one: a. True b. False 6. If Task A must complete before Task B can commence, the lag
5. Gantt charts cannot depict float.
Select one:
a. True
b. False
6. If Task A must complete before Task B can commence, the lag relationship is:
Select one:
a. Finish to Start
b. Start to Finish
c. Start to Start
d. Finish to Finish
7. "n analyzing crash opportunities for project activities, each activity is assessed by comparing the change in cost to the change in time.
Select one:
a. True
b. False
8. In classic project management, activity durations are often estimated based upon a 90% likelihood of successful completion, but in CCPM, the ___% level is used.
Select one:
a. 95
b. 75
c. 50
d. 25