Question: 6 . 5 The laboratory test in Problem 6 . 4 is used to develop field compaction specification for a highway project. A field unit

6.5 The laboratory test in Problem 6.4 is used to develop field compaction specification for a highway project. A field unit weight determination during the construction revealed that the in situ moist unit weight is 124lbft3 and the moisture content is 13.7%. Determine the relative compaction in the field.