Question: 7. A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of B and of C. B

7. A simple CPM network has five activities, A,
7. A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of B and of C. B is an immediate predecessor of D and of E. C is an immediate predecessor of E. Which of the following statements is TRUE? C) There are five paths in this network. O A) There are two paths in this network. OD) There are three paths in this network B) There are four paths in this network