Question: 7, An activity that has more than one dependency arrow flowing to it is termed a __________. a. parallel activity b. merge activity c. dummy

7, An activity that has more than one dependency arrow flowing to it is termed a __________.

a.

parallel activity

b.

merge activity

c.

dummy activity

d.

burst activity