Question: 9) If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, what is the
9) If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, what is the crash cost per A) $400 B) $2,000 C) $10,000 D) $20,000 E) $30,000