Question: 9. Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the

9. Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 5 weeks in the most economical way.

Activity

Normal Time (weeks)

Normal Cost ($)

Crash Time (weeks)

Crash Cost ($)

Maximum Weeks Reduced

Crash Cost per Week ($)

A

3 450 2 860 1 410

B

4 650 3 750 1 100

C

6 800 3 1,325 3 175

D

6 1,500 4 2,140 2 320

E

6 1,650 4 2,170 2 260

F

5 200 5 200 0 0

G

7 1,600 5 1,900 2 150

H

3 550 3 550 0 0

AON network diagram

9. Using the information provided in the table,

(If there is no amount for a box enter 0. All boxes must be filled.)

Reduce A by ____________ week(s), B by________ week(s), C by _________ week(s), D by _________ week(s), E by _______ week(s), F by ______ week(s), G by _________ week(s), H by ___________ week(s).

Total additional cost is ______________

B(4) E(6) A(3) C(6) G(7) H(3) D(6) F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!