Question: 9. Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the
9. Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 5 weeks in the most economical way.
| Activity | Normal Time (weeks) | Normal Cost ($) | Crash Time (weeks) | Crash Cost ($) | Maximum Weeks Reduced | Crash Cost per Week ($) |
|---|---|---|---|---|---|---|
| A | 3 | 450 | 2 | 860 | 1 | 410 |
| B | 4 | 650 | 3 | 750 | 1 | 100 |
| C | 6 | 800 | 3 | 1,325 | 3 | 175 |
| D | 6 | 1,500 | 4 | 2,140 | 2 | 320 |
| E | 6 | 1,650 | 4 | 2,170 | 2 | 260 |
| F | 5 | 200 | 5 | 200 | 0 | 0 |
| G | 7 | 1,600 | 5 | 1,900 | 2 | 150 |
| H | 3 | 550 | 3 | 550 | 0 | 0 |
AON network diagram

(If there is no amount for a box enter 0. All boxes must be filled.)
Reduce A by ____________ week(s), B by________ week(s), C by _________ week(s), D by _________ week(s), E by _______ week(s), F by ______ week(s), G by _________ week(s), H by ___________ week(s).
Total additional cost is ______________
B(4) E(6) A(3) C(6) G(7) H(3) D(6) FStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts