Question: a - 1 . Identify the critical path. multiple choice A - C - D - F A - C - E - F A
a Identify the critical path.
multiple choice
ACDF
ACEF
ABDF
a Identify the earliest start and finish for each task. Leave no cells blank be certain to enter wherever required.
b Calculate slack for every project activity. Leave no cells blank be certain to enter wherever required.