Question: A certain project has 11 activities, a budget to completion of $319K, and an anticipated duration of 8 months. The budgeted schedule for this project

A certain project has 11 activities, a budget to completion of $319K, and an anticipated duration of 8 months.

The budgeted schedule for this project and the earned value, in $1,000, as follow:

Activity

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Total

Planned

Earned Value

TOTAL MONTHLY PLAN

18

23

36

40

56

40

68

??

319

251

CUMULATIVE PLAN

MONTHLY ACTUAL

20

21

33

46

61

98

CUMULATIVE ACTUAL

At the end of June, the estimated COST to completion, in $1,000, is: