Question: A certain project has 11 activities, a budget to completion of $319K, and an anticipated duration of 8 months. The budgeted schedule for this project
A certain project has 11 activities, a budget to completion of $319K, and an anticipated duration of 8 months.
The budgeted schedule for this project and the earned value, in $1,000, as follow:
| Activity | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Total Planned | Earned Value |
| TOTAL MONTHLY PLAN | 18 | 23 | 36 | 40 | 56 | 40 | 68 | ?? | 319 | 251 |
| CUMULATIVE PLAN |
|
|
|
|
|
|
|
|
|
|
| MONTHLY ACTUAL | 20 | 21 | 33 | 46 | 61 | 98 |
|
|
|
|
| CUMULATIVE ACTUAL |
|
|
|
|
|
|
|
|
|
|
At the end of June, the estimated COST to completion, in $1,000, is:
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
