Question: QUESTION 3 A certain project has 11 activities, a budget to completion of $361K, and an anticipated duration of 12 months. The budgeted schedule for
QUESTION 3
-
A certain project has 11 activities, a budget to completion of $361K, and an anticipated duration of 12 months.
The budgeted schedule for this project and the earned value, in $1,000, as follow:
Activity
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug - ...
Total
Planned
Earned Value
TOTAL MONTHLY PLAN
15
23
36
40
56
21
66
?
361
206
CUMULATIVE PLAN
MONTHLY ACTUAL
16
21
33
47
60
54
CUMULATIVE ACTUAL
At the end of June, the estimated Time to completion, in months, is:
(i.e. the estimated number of months to complete the project from beginning to end as a decimal number; e.g. 3.76 months)