Question: A control chart plots 19 samples per day, 7 days a week. The process runs 24 hours per day and the chart is currently in

A control chart plots 19 samples per day, 7 days

A control chart plots 19 samples per day, 7 days a week. The process runs 24 hours per day and the chart is currently in control. 1. What is the probability of plotting 5 samples in a row in Zone B? a. 0.8145 b. 1.08 c. 0.02117 d. 0.005314 e. 0.001435 2. On average, an observation will fall into either Zone A or Zone B approximately once every hours. a. 1 b. 2 c. 3 d. 4 e. 5 f. 6