Question: A CPI or SPI value equals to one indicates that the project is Select one: A. Under cost or behind schedule. B. Over cost or
A CPI or SPI value equals to one indicates that the project is
Select one:
A. Under cost or behind schedule.
B. Over cost or ahead of schedule.
C. Under cost or ahead of schedule.
D. Over cost or behind schedule.
E. On cost or on schedule.