Question: A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take? Ask the team to raise blockers or impediments in daily meetings. Prioritize the tasks with high risks to reduce the number of iterations required Ask the team to challenge the project estimations for a faster delivery. Prioritize deliverables based on business value and define frequent releases