Question: a) Determine the critical path(s), execution time, and normal cost of the project. b) Calculate the cost slopes of each project activity. c) How much

a) Determine the critical path(s), execution time, and normal cost of the project. b) Calculate the cost slopes of each project activity. c) How much will it cost to advance the execution time of the work by 3 days? d) Make the graph TIME COST.

a) Determine the critical path(s), execution

Actividad Precedida por Tiempo normal (das) A 5 B 11 7 D A, B 8 E A, B, C 4 F A 17 G E 7 H D, F, G 6 I F 14 J H 8 Costo Normal ($) 9500 18000 12000 8000 1500 18000 4000 15000 7000 14500 Tiempo acelerado Costo Acelerado (das) ($) 4 10000 9 24000 5 13500 7 11000 3 1750 15 23000 5 7500 4 20000 12 9500 7 19500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!