Question: a) Determine the critical path(s), execution time, and normal cost of the project. b) Calculate the cost slopes of each project activity. c) How much
a) Determine the critical path(s), execution time, and normal cost of the project.
b) Calculate the cost slopes of each project activity.
c) How much will it cost to advance the execution time of the work by 3 days?
d) Make the graph TIME COST.
Graph, and perform step by step. Activity, Precedence, Normal Time, Normal Cost, Expedited Time, Expedited Cost. (table order). The method to use is PERT/COST