Question: a ) Determine the minimum cost required to achieve this deadline table [ [ Activity , table [ [ Normal ] , [

a) Determine the minimum cost required to achieve this deadline
\table[[Activity,\table[[Normal],[duration],[(days)]],\table[[Crash],[duration],[(days)]],\table[[Normal],[Cost]],Crash Cost,\table[[Immediate],[predecessors]]],[A,120,100,$12,000,$14,000,-],[B,20,15,$1,800,$2,800,-],[C,40,30,$16,000,$22,000,B],[D,30,20,$1,400,$2,000,C],[E,50,40,$3,600,$4,800,D,F],[F,60,45,$13,500,$18,000,B]]
 a) Determine the minimum cost required to achieve this deadline \table[[Activity,\table[[Normal],[duration],[(days)]],\table[[Crash],[duration],[(days)]],\table[[Normal],[Cost]],Crash