Question: a ) Develop the precedence diagram, calculating ES , EF , LS , LF , TF for each activity b ) Indicate the critical path

a) Develop the precedence diagram, calculating ES, EF, LS, LF, TF for each activity
b) Indicate the critical path
c) What is the shortest possible duration of the project?
d) What's the total float for activity I, and explain the meaning of using total float.
\table[[Activity,\table[[Duration],[(Working Days)]],\table[[Activity immediately],[following]]],[A,9,E, F],[B,11,H, I, J],[C,45,M],[D,30,N],[E,8,H, I, J],[F,17,G, J],[G,23,L],[H,10,K],[I,6,L],[J,10,L, N],[K,10,P],[L,14,P],[M,18,O, P],[N,25,R],[O,15,Q],[P,12,R],[Q,10,],[R,6,],[,,]]