Question: A direct time study was taken on a manual work element using the snapback method. The regular cycle consisted of three elements, a , b

A direct time study was taken on a manual work element
using the snapback method. The regular cycle consisted
of three elements, a, b, and c. Element d is an irregular
element performed every five cycles. The average values
for observed times and performance ratings are given for
the work elements.
Work element a b c d
Avg. obs. time (min)0.560.250.501.10
Avg. perf. rating 100%80%110%100%
Determine (a) normal time and (b) standard time for the
cycle (Allowance factor is 15%)