Question: A direct time study was taken on a manual work element using the snapback method. The regular cycle consisted of elements, a, b, c and
A direct time study was taken on a manual work element using the snapback method. The regular cycle consisted of elements, a, b, c and d. Element d is an irregular element performed every four cycles.
Work element a b c d
Observed time (min) 1.56 1.25 2.50 1.35
Performance rating 100% 90% 110% 85%
Determine the Normal time for the cycle. Select correct answer from below:
-
1.64 min
-
5.72 min
-
6.58 min
-
7.56 min