Question: A framework contract was signed with Interstellar Ops for the provision of maintenance and operation services on the central teleportation machine and its teleportation

A framework contract was signed with "Interstellar Ops" for the provision of

A framework contract was signed with "Interstellar Ops" for the provision of maintenance and operation services on the central teleportation machine and its teleportation portals. LS2 is ending in six months, the Technical Officer has observed increasing delays in the preventive maintenance plan, and an increasing number of breakdowns of the central teleportation machine. As a result, the system's overall availability is now below the required level and users are dissatisfied with the service level that Interstellar Ops and, to a certain extent, the Teleportation Operations Group are offering. In addition, CERN has observed an increase in non-conformities in sample checks performed both on preventive and corrective maintenance activities: The Technical Officer already discussed these issues with the contractor's team leaders several times. The Technical Officer also reviewed the contractor's QAP(Quality Assurance Program), in particular the working procedures, which were found to be correctly drafted. For the past few months, in order to facilitate an improvement in the service level, CERN's technical supervisors have spent more and more time accompanying the contractor's personnel to give specific technical advice on how some specific maintenance activities should be performed, in particular for the replacement and handling of Kryptonite magnetic cores. Still, the service level has not improved. If the situation does not improve soon, the Technical Officer intends to start applying penalties. Please list the problems and root causes. What would be your recommendations? You need to discuss this point at least by 200words. Give appropriate reference and citation for your answer (b) Discuss the impact of Contract Type Versus Risk

Step by Step Solution

3.46 Rating (146 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The problems in this situation include Delays in the preventive maintenance plan This is likely a result of the contractor not adhering to the schedule agreed upon in the contract or not having enou... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!