Question: A local project being analyzed by PERT has 1 0 activities, 9 of which are on the critical path. If the estimated time along the

A local project being analyzed by PERT has 10 activities, 9 of which are on the critical path. If the estimatedtime along the critical path is 105 days with a project variance of 25, what is the probability that the project will becompleted in 100 days or less? (please answer to four decimal places)