Question: a m Time estimates Activity Optimistic Most Likely Pessimistic b A 38 50 62 D 19 25 31 F 62 65 68 B 90 99

a m Time estimates Activity Optimistic Most

a m Time estimates Activity Optimistic Most Likely Pessimistic b A 38 50 62 D 19 25 31 F 62 65 68 B 90 99 108 E 91 100 115 85 100 115 A D F End Start B E What is the estimated variance in the time for activity E? 3 days 16 days 24 days a 2 days 4 days