Question: Time estimates Activity Optimistic Most Likely Pessimistic a m b A 38 50 62 D 19 25 31 F 62 65 68 B 90 99

Time estimates Activity Optimistic Most Likely

Time estimates Activity Optimistic Most Likely Pessimistic a m b A 38 50 62 D 19 25 31 F 62 65 68 B 90 99 108 E 91 100 115 85 100 115 A D F End Start B E What is the estimated standard deviation of the expected time for path B-E? 71 days 4.58 days 5 days 25 days 21 days