Question: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start A Precedes A,B,C D E End 38 62 108 115

Consider the following work breakdown structure:
Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start A Precedes A,B,C D E End 38 62 108 115 B 90 85 50 99 100 25 100 65 C D E F 19 31 91 End End 115 68 F 62 What is the estimated expected (mean) time for project completion? 199 days 100 days 200 days 440 days 140 days