Question: A network diagram for a project is different from a Gantt chart for a project in which of the following ways? a.) A network diagram
A network diagram for a project is different from a Gantt chart for a project in which of the following ways? a.) A network diagram is the basis for creating a risk management plan. b.) A network diagram is used to display all of the project work. c.) A network diagram is better for comparing relationships among project activities. d.) A network diagram is the basis for creating the project schedule.