Question: A partial information about a project is shown below. Activity M; 52 days; IP = G, H Activity N; 55 days; IP = G, H
A partial information about a project is shown below. Activity M; 52 days; IP = G, H Activity N; 55 days; IP = G, H Activity P; 58 days; IP = K Activity Q; 41 days; IP = M Activity R; 53 days; IP = N, P It has been calculated that LF(Q) = 198 and LF(R) = 208. Find the value of LF(G)