Question: A partial information about a project is shown below. Activity M; 43 days; IP = G, H Activity N; 35 days; IP = G, H

A partial information about a project is shown
A partial information about a project is shown below. Activity M; 43 days; IP = G, H Activity N; 35 days; IP = G, H Activity P: 51 days; IP=K Activity Q; 62 days; IP = M Activity R; 64 days; IP = N, P It has been calculated that LF(Q) = 196 and LF(R) = 207. Find the value of LF(G)